Phase Approach - Agreed work at meeting "16/02/25"
- STEP 1
Quotes for the new work should include a detailed breakdown of labour and material costs.
- STEP 2
As agreed in the meeting, £15,000 must be raised before any work can begin.
Phase 1
- Plaster brick wall nearly built
- Plaster ceiling and pillars
- Paint full Janaza hall
Phase 2
- Concrete all Janazah area at 5 inch concreate
- The area where trolly will passes
- Dig 7 Inch
- 2 Inch hardcore
- 5 Inch concreate
- Reinforced steel bars 6 - 8mm thick
Suggestions
- Grill work is on hold and will be reconsidered at a later date.
- No wall to be built infront of Janazah area - Leave open
STOPPED till further notice
- Fill land with sand free
- Transport cost 1000 rupees
- 84 trollies = 84,000 rupees
Note:
The quoted price may vary based on the builder’s recommendations once work begins.
"Please keep this in mind"
Note
Added 10% - 15% contingency rough estimate cost = 45LKH